CNC Turning Tolerance vs Cost The Drawing Says Fifty Microns, the Quote Is Priced at Twenty
A buyer sends a drawing with a diameter at plus or minus 0.05 mm, receives a quote, and then notices that the supplier’s capability statement talks about plus or minus 0.02. The obvious question is why the price is not lower, since the requirement is looser than the capability. The answer is that the price is not set by the tolerance on the drawing; it is set by the process that produces the part, and that process has a natural capability which it holds whether or not the drawing asks for it. Tightening a process costs money. Loosening a requirement below the process’s natural capability saves nothing, because the process does not get cheaper when the tolerance is relaxed. This is the core of the CNC turning tolerance vs cost relationship, and it is routinely misread in both directions.

The CNC Turning Tolerance vs Cost Curve Is Flat, Then Steep
Plot cost against tolerance and the shape is not a straight line. At the loose end the curve is flat: a tolerance of plus or minus 0.2 and a tolerance of plus or minus 0.05 cost almost the same, because a CNC lathe holds both without any special measure. In the middle the curve starts to rise: plus or minus 0.02 needs a stable process, in-process gauging, and a temperature-controlled environment. At the tight end it rises steeply: plus or minus 0.005 needs a different process, a different machine condition, and a different inspection regime, and the cost can double or triple for a halving of the band.
The flat section is the part that buyers do not believe. A drawing at plus or minus 0.2 and a drawing at plus or minus 0.05 produce quotes that differ by a few percent, because the machine, the program, the setup, and the inspection are the same. The tolerance is not a cost driver in that range; the part geometry is. A buyer who relaxes a tolerance from 0.05 to 0.2 expecting a discount is asking the supplier to charge less for the same work, and the supplier who agrees is either discounting for commercial reasons or was overpriced before.
The steep section is the part that suppliers do not explain well. A tolerance of plus or minus 0.005 on a fifty millimetre diameter is tighter than IT5, which means it is not a turning tolerance at that size. The cost does not rise by twenty percent; it rises by a factor that reflects a grinding operation, a separate setup, and a queue. A buyer who tightens a tolerance by a factor of four in that range and expects a proportional price increase is going to be surprised by the quote.
Why the Quote Reflects the Process, Not the Number
A shop quoting a turned part chooses a process before it chooses a price. The process is determined by the material, the geometry, the quantity, and the tightest feature on the part. Once the process is chosen, the price follows from its cost, and the tolerance on any individual feature is largely irrelevant unless it is the feature that drove the choice.
That is why a plus or minus 0.05 diameter on a part whose tightest feature is plus or minus 0.02 is priced at the 0.02 process. The part already needs the tighter process for the other feature, so the loose diameter comes along for free. Quoting it separately would be artificial, and quoting it lower would be a discount dressed as a technical argument.
The converse is the case that generates complaints. A part with every feature at plus or minus 0.05 and one feature at plus or minus 0.01 is priced at the 0.01 process for the whole part, because the part is set up once and the tight feature dictates the machine condition, the tooling, and the inspection. The buyer sees one tight callout and a price that reflects the whole part, and concludes that the supplier is overreacting to a single dimension. The supplier is not overreacting; it is pricing the setup.
Capability, Not Tolerance, Is What You Buy
Capability is a statistical property: the width of the process distribution relative to the tolerance band, expressed as a capability index. A process with a capability index of 2.0 produces a distribution whose six sigma width is half the tolerance band, which means defects are effectively impossible. A process with an index of 1.0 has a distribution as wide as the band, which means roughly three parts per thousand fall outside it.
This is the number that determines the price, because it determines the inspection and the scrap. A process at index 2.0 can be sampled; a process at index 1.0 must be inspected, and inspected parts that fail must be scrapped or reworked. The cost of that inspection and scrap is real, and it is the reason a shop will choose a process that holds plus or minus 0.02 for a plus or minus 0.05 requirement: the tighter process is cheaper in total because it removes the inspection and the scrap, even though the machine rate is higher.
This is counter-intuitive and it is the heart of the matter. Holding a loose tolerance with an unstable process is more expensive than holding a tight tolerance with a stable one, because the unstable process requires a census inspection and generates scrap. A shop that quotes a plus or minus 0.05 part at a price that reflects a plus or minus 0.02 process is often quoting the cheaper total, not the more expensive one.
| Band | Process | Inspection | Scrap risk | Relative cost |
|---|---|---|---|---|
| ±0.10 | Standard turning, no compensation | Sample, 5 per lot | under 1 percent | 1.00 |
| ±0.05 | Standard turning, tool compensation | Sample, 5 per lot | 1 to 2 percent | 1.05 |
| ±0.02 | Controlled turning, thermal stability | In-process gauge, 100 percent | 2 to 4 percent | 1.25 |
| ±0.005 | Grinding or precision boring | Post-process, 100 percent, controlled room | 3 to 6 percent | 2.10 |
The table is worth reading twice. The step from plus or minus 0.10 to plus or minus 0.05 costs five percent, which is why relaxing that tolerance buys nothing. The step from 0.02 to 0.005 more than doubles the cost, which is why tightening that tolerance is a design decision with a price attached. And the middle step, 0.05 to 0.02, costs twenty percent, which is the step that most parts sit on without anyone realising it.
Where the Twenty Percent Goes
Half of the twenty percent is inspection. A hundred percent in-process gauging requires a gauge at the machine, a routine in the program, and an operator who reacts to the reading. On a five hundred piece lot that is a real labour cost, and it is the cost that a plus or minus 0.10 part does not carry.
The other half is scrap and rework. A process at plus or minus 0.02 that drifts produces parts outside the band, and those parts are either reworked or scrapped. The scrap rate at that tolerance is two to four percent even in a good shop, and the cost of that scrap is carried by every good part. This is the tolerance cost curve in practice: the visible machine cost rises gently and the invisible quality cost rises steeply, and the sum is what the quote reflects.
The Same Curve at Different Quantities
The tolerance-cost curve shifts with quantity, and the shift is not uniform along its length. At the loose end, quantity barely matters, because the process is the same at fifty pieces and at fifty thousand. At the tight end, quantity matters enormously, because the tight process requires a setup, a qualification run, and an inspection plan that are fixed costs. A plus or minus 0.005 part at fifty pieces carries the entire qualification in fifty parts; the same part at five thousand spreads it across a hundred times as many.
This produces a result that confuses buyers comparing quotes at different quantities. A shop may be cheaper at five thousand pieces on a tight part and more expensive at fifty, not because it is inconsistent but because the fixed cost of the tight process is being divided by a different number. The comparison that matters is at the quantity actually being ordered, and a quote for a different quantity is a different product.
The practical consequence is that the tightest tolerance a part can economically carry depends on the volume. A prototype at plus or minus 0.005 is a grinding job with a one-off setup, and the price reflects that. A production part at the same tolerance is a grinding job with an amortised setup, and the price is a fraction. A buyer who prototypes at a loose tolerance to save money and then specifies a tight one for production has reversed the logic: the prototype is where the tight tolerance is expensive, and production is where it becomes affordable.
What a Buyer Should Do With This
First, identify the features that actually need the tight tolerance. A part with four toleranced features where only one is functional is a part that is being priced at the tightest feature for no reason. Relaxing the other three changes nothing, which is useful to know even though it saves nothing.
Second, ask what the price would be at one grade looser on the tightest feature. If the answer is a meaningful reduction, the tolerance was driving the process and the design should be questioned. If the answer is no change, the tolerance was free and the design is fine. The question costs one email and it produces information that a drawing review cannot.
Third, accept that the flat part of the curve is flat. A supplier who quotes the same price for plus or minus 0.1 and plus or minus 0.05 is not being difficult; the two are the same job. A supplier who quotes a large premium for that step is either using an unstable process or is padding, and either is worth knowing before the second order.
Fourth, understand that the price is a package. A quote that includes a first article, a material certificate, and a dimensional report is not comparable to one that includes machining only, and on tight work the inspection package is a large share of the total. The Xometry CNC machining tolerance guidance is a reasonable reference for what the market treats as standard at each band, and comparing a factory quote against it shows which parts of the package are being charged separately.
Why the Answer Is Sometimes a Different Process
There is a case where the honest answer to a tolerance question is that the process should change. A part at plus or minus 0.05 on a forty millimetre diameter is a comfortable turning job. The same tolerance on a hundred and fifty millimetre diameter is a different proposition, because the thermal growth over that size is larger than the band and the machine’s geometry error becomes significant. At that point the answer is not a tighter process but a different one, and the price reflects the change.
The same applies to a tolerance that must be held across a long length. A diameter at plus or minus 0.02 is a turning tolerance; the same band held over three hundred millimetres of length is a straightness and taper requirement, and it needs a steady rest, a temperature-controlled environment, and a different inspection. The number on the drawing is the same and the process is not, which is why the tolerance alone never determines the price.
The vocabulary for the difference between a size requirement and a form requirement is the one used in this explanation of the difference between straightness and flatness, and a drawing that conflates the two will always be quoted at the more expensive of the two.
What the Supplier Should Say
A supplier that answers a tolerance question with a number has answered half the question. The useful answer names the process, the inspection, and the scrap risk, and states which of them the tolerance changed. That answer lets a buyer make a design decision rather than a price decision, and it is the difference between a supplier and a vendor.
The CNC lathe services capability statement should give the achievable band by feature type and size, because a single figure conceals the fact that the band widens with diameter. A shop that quotes plus or minus 0.02 as a blanket figure is quoting its best case, and the best case is achieved on a twenty millimetre diameter in a temperature-controlled room, not on a hundred and fifty millimetre flange in July.
The parts that sit at the boundary between turning and grinding are the ones where this conversation pays, and the CNC turning parts manufacturer capability summary is organised to show which features are turned and which are ground, because the boundary is where the price changes.
A tolerance is not a number that a supplier meets or misses. It is a specification of a process, and the process has a cost that is mostly independent of the number. The quote reflects the process, which is why a looser drawing does not always produce a cheaper part, and why the question worth asking is not what the tolerance is but what it is for.